Approx. Time Required |
Description of Work |
4 Days |
Site Preparation - Clear the land and install batter boards with string for reference |
4 Days |
Excavation - Dig basement and trenches for footings, excavate trenches for water, sewer, gas and utility lines |
10 Days |
Foundation - Pour all footing, pour/lay foundation walls, waterproof below grade, install drains, install perimeter insulation (optional) |
Temporary Electric - Have electric company install temporary electric service before framing begins |
|
10 Days |
Frame House - Install floor system, build and set exterior walls, frame roof system, install roofing, set interior partitions, install exterior siding, install windows and exterior doors. |
4 Days |
Rough Plumbing - Locate plumbing fixtures and install all piping for sewer, water and gas lines |
5 Days |
Heating/Air Conditioning - Install HVAC System and all ductwork |
5 Days |
Rough Electric - Have electric company install meter. Install service panel, connect to meter and ground, run wiring to fixtures locations |
4 Days |
Concrete Floors - Pour garage and basement pads after proper base and reinforcement has been installed. Outside patios should wait until drywall is finished |
8 Days |
Insulation and Drywall - Install insulation, hang and finish drywall |
10 Days |
Interior Finishing - Install interior doors, paint, install kitchen cabinets, bathroom vanities and all trim |
3 Days |
Finish Electric, Plumbing and HVAC - Install light fixtures, receptacles, vent fans, doorbells, switch/receptacle plates, toiliets, sinks, faucets, vents and grills |
3 Days |
Flooring/Carpeting - Install finish flooring and/or carpeting |